BUZAU CRANG 110/20KV POWER STATION
BUZAU CRANG 110/20KV POWER STATION
The works included:
- Installation of LES 20 kV power lines – 1,5km
- Reconstruction of the medium voltage grids with jointing and terminlas (34 pcs) for the interconnection with substations
- Installation of new MV equipment (15 cells) and 20 kV switchgear connections
- Refurbishment of the control room
- Construction of concrete foundations
- Replacement of the control-command panels and secondary circuit cales (command-protection)
- Replacement of the control-protection cabinets for the 110kV equipment and their integration into the SCADA telecontrol system, including the installation of the telecommunication equipment
- Replacement of the DC installations for the station (battery and rectifier), including LV internal services (AC and DC)
- Fire extinguishing system, access and surveillance system
Electrogrup succsessfully completed:
- Project Management – our teams coordinated the entire work
- Health & Safety coordonation
- Primary and secondary 110, 20, 0.4kV equipment installation
- SCADA sustem
Challanges
- Working in an operating power station, with underground HV and MV cables and HV equipment
- Provisionally control circuits and ensuring the consumer`s power supply during the execution of the works