MODERNIZATION OF THE 110/20 KV DOICEȘTI STATION
A photovoltaic park was built, with an installed power of 30 MW, made with 36,800 Trina panels – 655 W, 122 Huawei inverters – 215 kW, 9 Huawei 20 / 0.8 kV – 3.4 MVA transformer stations and the 110 / 20 kV Doicești transformer station was modernized, it being equipped with a 63 MVA transformer
Built area: 30 ha
Start: 2023
Completion: August 2023