POWER PLANT CEG 4+5, CAMPIA TURZII
Location: Câmpia Turzii, str. Laminoristilor, no. 157, Cluj county
The project consists in increasing the production capacity of the Nova Power & Gas Electroenergetic Ensemble consisting of two CEG1 + 2 Power Plants executed in 2021 and those that will be built this year, respectively CEG 4+5. The installed power of the 4 groups is 26.88 MW (2×6 .72MW+2×6.72MW) Construction includes: metal structure, concrete platforms, hydrocarbon tanks, access roads, MV cell room, foundations for transformers 10.5/20kV, T4 and T5.
Built area: 700 sq m
Start: 12.12.2021
Completion: 30.06.2022