The renovation and construction works within the existing operating 110kV power station included: replacement of the existing cells, of the relay room, MV switchgear room, LV services and electrical equipment
Civil works included:
- Refurbishment of the control and connection building;
- Replacing of the existing foundations;
- Replacing the concrete old structure with a steel structure;
- 110 / 20 kV Power Transformer;
- Site works: yard, access roads, alleys, drainage;
Electrogrup successfully implemented:
- Project Management – our teams coordinated the entire work;
- Health and Safety coordination;
- Primary and secondary 110,20, 0.4 kV equipment installation;
- SCADA system and commissioning;
Challenges:
- Working in a live substation with overhead power lines, underground cables and HV equipment;
- Provisionally control circuits;